Preparations to Remove the Boiler

A work session was arranged for Saturday, January 7, 2012 to continue work started before the holidays on the Chicago & Northwestern no. 1385. The primary goal in these recent work sessions have been to remove exterior appliances from the locomotive boiler and frame. This work is being done in preparation for boiler removal from the frame and the shipment of the running gear to a shop for rebuild. Having sat idle and exposed to the elements for much of the time since it last operated in June of 1998, removal of many of the pieces have proven to be no easy undertaking and to make matters even more difficult, items like the running board brackets have not be removed from the boiler in many decades.

The crew for the day was led by Ed Ripp and Pete Deets. Assisting were Kelly Bauman, Richard Colby, and engine house first-timers Adam Stutz and Jeffrey Lentz. Jim Busse was also on hand and performed some much-needed cleaning and organization of the engine house and surrounding area.

With the 1385 parked in the engine house and the large south door open to let in the sun and unseasonably mild temperatures, work began. Pete, Ed and Richard all took turns climbing into the smokebox to clean rust from the blast pipe and smokestack mountings. Removal of the engineer side air reservoir brackets also took place. Work proceeded slowly as the rust necessitated most bolts be cut with a torch.

Close quarters between the 1385 and the engine house wall on the fireman side of the locomotive required that the R-1 be towed by MCRY no. 4 to a location just outside of the engine house to reduce fire risk from the shower of sparks. Once outside, work was able to proceed on removal of the air reservoir tank brackets and running boards. Work also began on the removal of the smokestack. With the more advanced work left largely to Pete and Ed, restoration newcomers Richard, Adam and Jeffrey took on the removal of the pilot support brackets at the front of the locomotive, a job suited to their flexibility.

Work continued as darkness descended. Finally, with too little light to safely continue, work was halted at about 6 pm and the 1385 was rolled safely back into the engine house to await the next work weekend.

 

Comments are closed.