Mid-Continent Railway Museum

North Freedom, Wis.

Mid-Continent Railway Museum logo banner with images of train cars and people.
  • Home
    • Home Page
    • News
    • Join Our Email List
    • Media
  • Plan Your Visit
    • Buy Tickets
    • Train Ride/Museum Info
    • Special Events
      • Autumn Color™ Weekend
      • Pizza Limited
      • Harvest Flyer
      • Pumpkin Special™
      • Root Beer Float Flyer
      • Santa Express™/Holiday Flyer
      • Stars and Stripes Special
      • Vintage Rail Car Tours
    • Cancellation Policy
  • Gift Shop
  • Restorations
    • Major Projects
    • Steam Status
      • Overview
      • C&NW #1385 Status Updates
      • Western Coal & Coke #1 Status Updates
      • Dardanelle & Russellville #9 Status Updates
    • Car Shop
      • General Updates
      • DSS&A Sleeper DULUTH
      • EJ&S #2
      • Badger #2
      • Copper Range #25
      • MLS&W #63
      • Copper Range #60
  • Equipment Roster
    • Equipment Roster Home
    • Steam Locomotives
    • Diesel/Other Locomotives
    • Wooden Passenger Cars
    • Steel Passenger Cars
    • Wooden Freight Cars
    • Steel Freight Cars
    • Cabooses
    • Service Equipment
    • Former Collection Items
  • Resources
    • Online Archives Home
    • Wooden Car Builders
    • MCRM Newsletters
    • Gazette Archive
    • Audio Archive
    • Video Archive
    • Wallpaper
    • Kids Page
      • Kids Page
      • What Makes A Diesel Locomotive Work?
      • What Makes A Steam Locomotive Work?
  • About Us
    • Contact Us
    • About Mid-Continent
    • Board of Directors
    • Department Leaders
    • Our Staff
    • Become a Member
    • Volunteer
    • Employment
    • Tour of Grounds
    • Local History
    • Mid-Continent Timeline
    • Privacy Policy
  • Donate

Post navigation

← Older posts
Newer posts →

Riveting Work Weekend

Mid-Continent Railway Museum Posted on November 18, 2006 by Jeffrey LentzApril 15, 2015

Work this weekend included installing 8 rivets in the WC&C #1 fire box patch. Friday afternoon and Saturday morning was spent in preparation. A backer plate was fabricated. Then a test plate with 4 holes was formed and used to determine the rivet length needed. All the tools were lined up and test hole riveted. Testing went perfect and all 8 rivets in the patch were installed in an hour and 15 minutes.

Rivet crew of five; Bob Ristow, Pete Deets, Roger Hugg, Ed Ripp and
Jim Connor.

Pictures show Pete Deets welding on the backer plate. Pete and Bob Ristow reaming rivet holes. Ed Ripp running the rivet gun. Completed patch with 8 rivets installed. The patch will be welded in place in the near future. Also a picture of Bob’s progress on the boiler check valves.

–Jim Connor




Tagged firebox, riveting, Western Coal & Coke 1

Lund Machine and Tool Works on Firebox Replacement Pieces

Mid-Continent Railway Museum Posted on October 23, 2006 by Jeffrey LentzApril 15, 2015

Some progress finally to report. Jim Connor took some photos and hopefully will forward them to you. Lund Machine and Tool arrived Monday after noon. Work started immediately on the firebox replacement pieces. The old sheet pieces were removed in the area of the new rear tube sheet, a 1/2″ thick plate with the keyhole shape was fitted into place. The engineers rear corner patch was fabbed and is ready for 9 rivets. The front tube sheet was removed.

The swing links for the front truck have new bushings installed and work continues on disassembling and inspection.

–Bob Ristow

Photos by Jim Connor.




Tagged firebox, riveting, tube sheet, Western Coal & Coke 1

Dome Surfacing Machine

Mid-Continent Railway Museum Posted on September 10, 2006 by Jeffrey LentzApril 15, 2015

New member Randy Way, Jim Connor, and Bob Ristow where able to set up the dome surfacing machine enabling truing of the gasket surface. Mark Jones joined Bob on Sunday, the ‘cut’ on the dome was dressed up and a ‘new’ storage box was built for the surfacing machine. The new box is about 3/4 the size of the old one and will facilitate storage since it can now fit thru a door. Several front tube sheet rivets were drilled in preparation for removal.

–Bob Ristow

Jim Connor photos.




Tagged riveting, tube sheet, Western Coal & Coke 1

C&NW 1385 Steam Status

Mid-Continent Railway Museum Posted on June 29, 2006 by Jeffrey LentzApril 11, 2015

C&NW #1385’s initial restoration efforts were documented within the pages of the Mid-Continent Railway Gazette and Mid-Continent’s The Steamer! newsletter and were not documented online. The following is an overview of #1385’s status written for the website as of June 29, 2006.


The image most people have of Mid-Continent involves the Chicago & North Western #1385 under steam, pulling either the Prosperity Special or the Circus Train or one of our own special excursions like Snow TrainTM or the Santa ExpressTM. The power of this image is so strong that museum guests still come here expecting to see the R-1 sitting in front of the depot, ready to make the day’s runs, even though she has been out of service since June of 1998.

We knew several years ago that her time was limited and began a fund raising campaign in 1996 entitled “Help Steam Live.” The campaign goal was a mere $250,000, when we thought the needed repairs would simply be tube and flue replacement plus patching the interior side-sheets of the firebox. But once the work commenced, the extent of the firebox damage from over eighty years of service became apparent. The result of a visual inspection by the State’s boiler inspector was the condemnation of the firebox.

While Mid-Continent’s volunteer shop crews wrestled with the decisions on how to proceed with the repair work, Federal guidelines for steam boiler operation changed, mandating even further major repairs. The museum engaged Steam Services of America in 2001 to perform a complete inspection of the boiler in light of these new requirements. The result was a significant expansion of the repair plan to encompass a major overhaul of the entire boiler. And the new price tag approached $750,000, well beyond the money raised by the “Help Steam Live” campaign. The R-1 was parked in favor of repairing less costly locomotives.

Still the museum was holding a significant amount of money restricted for the purpose of restoring this specific locomotive to operating condition. So in 2004 an agreement was entered with Deltak Construction Services of Plymouth, MN for the manufacture of a completely new boiler using all-welded construction techniques. The cost of $415,000 proved to be significantly lower than the cost of repairing the old boiler. And the long-term maintenance cost would also be less, insuring the R-1’s ability to operate far into the future.

Phase 1 of this program is now complete with Deltak delivering the engineering study and approved boiler drawings to the museum. Phase 2 will be the purchase of the needed materials. And Phase 3 will involve the boiler’s actual construction at Deltak’s shop, concluding with a successful hydro test.

When finished, the C&NW #1385 will be the most expensive of the three steam locomotives currently under repair. And that is why she is at the end of the list in terms of priority. But no concept of a steam program at Mid-Continent has ever been considered that would exclude the R-1 from being returned to operating condition. She is the gem of the steam locomotive collection.

View a history of C&NW #1385 here.

This drawing of an Omaha Road Class I-1 boiler, a sister engine to #1385, shows the portions of the boiler involved in future boiler work: firebox (yellow), throat sheet (blue), and boiler barrel (red).
C&NW #1385 in April 2001.

C&NW #1385 firebox exterior with cab removed.
Interior view of C&NW #1385’s boiler shell, showing longitudal braces. Rear tube sheet can be seen in background.

Looking toward rear of C&NW 1385’s firebox. Circular opening is firebox door. Firebox sidesheet can be seen at left, a portion cut away.

Looking forward at the rear tube sheet from inside firebox. Smaller holes are the flues; larger holes are for superheater tubes. All tubes have been removed from the boiler.

Tagged boiler, C&NW 1385, firebox, fundraising, restoration

Barrel Patch Riveting Projects Completed

Mid-Continent Railway Museum Posted on May 13, 2006 by Jeffrey LentzApril 15, 2015

Last weekend was another sucessfull riveting party! Over 40 rivets were installed completing all three barrel patch riveting projects. Only 3 of the 200 rivets installed over Spring Fling had to be replaced! Not bad for a bunch of rookies.

In addition, much work was completed on the DL&W combine #425. The truck and bolster were readied for installing back under the combine. Center plate and draft gear framing was repaired. The truck was actually rolled under the car on Monday, Tuesday work continued to repair the center sill/draft gear superstructure. It is anticipated that the car will be finished by this weekend.

Thanks to all who assisted in the above projects…your efforts do not go un-noticed.

May 22, Jeff Lund will return to finish the installation of the rear tube sheet. This will leave only the front tube sheet and rear firebox corner to require TLC by the welder.

Stay tuned for additional info and project updates…. “We can do this!”

–Bob Ristow

Tagged boiler, riveting, Western Coal & Coke 1

Post navigation

← Older posts
Newer posts →
QUICK LINKS
PLAN YOUR VISIT
BUY TICKETS
GIFT SHOP
DONATE
JOIN OUR EMAIL LIST
VIEW WEBCAMS
Live view of North Freedom depot

Contact Us

Mid-Continent Railway Museum
P.O. Box 358
E8948 Museum Road
North Freedom, WI 53951
Office phone: 608-522-4261
or 800-930-1385
E-mail: inquiries@midcontinent.org

Recent News

  • “Last Spike” Ceremony
  • Engine House Track #2 Update
  • 1385 Steam and Air Line Installation/Donation Update
  • #1385 Cab, Smoke Stack, and Hand Rail Installation/Donation Update
  • Your Help is Needed to Bring the C&NW #1385 Home Again!
©2025 - Mid-Continent Railway Museum - Weaver Xtreme Theme Privacy Policy
↑