EJ&S #2 Restoration Update – July 3, 2019

Work on the East Jordan & Southern #2 continues at a steady pace. This past weekend we had a great turnout during the work session, allowing us to work on several projects including the EJ&S #2 which was led by Pete B. and Bill. F.

Work focused on the west side of the car. Tasks included installing the window sills, window lentils, and the panels between the windows. New window stops for the west side of the car were also produced and all the pieces primed.

Pete B. making more progress on the EJ&S #2. Bill Buhrmaster photo.

EJ&S #2 Restoration Update – June 17, 2019

In the May work session we decided to remove the west side letter board, siding above the window sill and the window sill. Work was then started on fabricating new window sill material.

During the June 14 and 15th work session work on the window sill was completed. This included fastening an inner trim piece to the sill and then attaching the sill to the belt rail. The next steps include installing new siding above the window sill and re-installing the top fascia and letter board.

Peter B.
Restoration Department